Florida: Update on "Pay-When-Paid" Clauses
Overview
"Pay-When-Paid"
and "Pay-If-Paid" clauses are common, contingent payment provisions included in
construction contracts. As compared to
traditional contract terms, which require payment to a subcontractor within a
period of time after performance of the work, these clauses make a contractor's
obligation to pay its subcontractors conditional on payment by the owner. In other words, these provisions protect a
contractor by postponing its payment obligations to a subcontractor until it
receives payment from the owner.
In Article 409 (Vol. 15, No. 13) of this newsletter, we
analyzed the decision of the United States Court of Appeals for the Fourth
Circuit decision in Moore Bros. Co. v.
Brown & Root, Inc. and Highlands Ins. Co., 207 F.3d 717 (4th Cir.
2000). In Moore Bros., the court held that a surety could not invoke a
"Pay-If-Paid" clause in a subcontract as a defense to its liability on a
payment bond. As noted in that article,
the decision in Moore Bros.
illustrated that parties to a construction project need to pay careful
attention to the language in the contract and bond documents to ensure that the
parties' intent with regard to risk shifting is accurately reflected. The article also recommended that parties to
a contract review applicable law to determine the effectiveness (and
enforceability) of these provisions.
A recent decision issued by Florida's Fourth District
Court of Appeal examined a similar issue in the context of a "Pay-When-Paid"
clause. Everett Painting Co. v. Padula &Wadsworth Constr., Inc., 856
So. 2d. 1059, (Fla. 4th DCA 2003). In
evaluating this issue under Florida law, the court illustrated the same lessons
learned in Moore Bros. That is, the
decision underscored the importance of ensuring that the contract and bond
documents accurately reflect the parties' intentions and of knowing the
applicable law in a given jurisdiction.
Factual Background
In
December 1997, Everett Painting entered into a written subcontract with Padilla
& Wadsworth ("P&W") to perform painting services at "Driftwood Middle
School". This project qualified as a
"public project" under Florida Statute §255.05 and, under the terms of the
statute, P&W was required to obtain both a payment bond and a performance
bond on the project. P&W obtained
the bond from Travelers Insurance Company (the Surety).
The
subcontract between Everett Painting and P&W contained a "Pay-When-Paid"
clause, which provided "that final payment from the owner is a condition precedent
to Contractor's obligation to make final payment to Everett Painting." After completing the project, Everett
Painting requested final payment due under the contract. When P&W refused payment, Everett
Painting filed suit against the contractor and the Surety seeking payment in
the amount of $11,471.50.
The
trial court entered a summary judgment in favor of P&W and the Surety. According to the court, the "Pay-When-Paid"
clause in the subcontract barred Everett Painting's claim because at the time
the suit was filed the contractor had not yet received final payment from the
owner. Everett Painting appealed the
trial court's decision to the Florida's Fourth District Court of Appeal.
Decision on Appeal
The
Florida Fourth District Court of Appeal affirmed the trial court's decision
with respect to Everett Painting's claim against P&W, but reversed the
ruling with respect to the Surety. In reaching its decision, the appellate
court specifically addressed whether the "Pay-When-Paid" clause of the
subcontract precluded Everett Painting from recovering on its payment bond
claim.
As a threshold
matter, the appellate court reviewed the language of the subcontract to
determine the applicability of the "Pay-When-Paid" clause. Finding the clause clear and unambiguous,
the court held that the provision was binding on the parties to the
subcontract. In other words, the court
determined that "final payment from the owner [was] a condition precedent to
Contractor's obligation to make final payment to Everett Painting." Because P&W had not yet received final
payment from the owner, Everett Painting was not entitled to payment from the
contractor. Accordingly, the appellate
court affirmed trial court's ruling in favor of the contractor on the claim
under the subcontract.
However, the
"Pay-When-Paid" provision did not bar Everett Painting's claim against the
Surety on the payment bond. That is,
the appellate court recognized that "[a] payment bond is a separate agreement
from the contract and an inability to proceed against the Contractor does not
necessarily prevent recovery on the bond."
Accordingly, the court concluded that the trial court should have
allowed Everett Painting to pursue its claim against the Surety.
As an aside, the
appellate court noted that Section 713.245 of the Florida Statutes allows a
surety to limit its liability by including conditional payment language in
certain payment bonds. These
"conditional payment bonds" are allowable only if the contractor and
subcontractor include a similar limitation in the subcontract. In order to create a "conditional payment
bond", the surety must include specific language as prescribed by the statute.
Specifically, Section 713.245 states that the front page of the bond must
contain the following statement in at least 10-point type:
This
bond only covers claims of subcontractors, sub subcontractors, suppliers, and
laborers to the extent the contractor has been paid for the labor, services, or
materials provided by such persons.
This bond does not preclude you from serving a notice to owner oR filing
a claim of lien on this project.
Because the bond
agreement was not submitted into the record, the court could not determine
whether the Surety included this necessary language showing its intention of
creating a "conditional payment bond."
Nevertheless, even if the bond did contain the requisite language
prescribed by Section 713.245, the surety did not have the ability to limit its
liability on the public project, which gave rise to this action. The payment bond on this school project was
issued pursuant to Section 255.05, which does authorize to use of a conditional
payment bond on public projects. On the
contrary, this provision "seeks to protect subcontractors and suppliers by
providing them with an alternative remedy to mechanics liens on public
projects."
As a practical
matter, the successful defense to the claim on the subcontract may provide the
general contractor limited or no economic protection. Since it is likely that the general contractor provided the
payment bond surety a broad form indemnity, any recovery on the bond will
eventually become the subject of an indemnity claim by the surety.
Comment
The
court's holding in Everett Painting
demonstrates the importance of carefully reviewing and understanding the
significance of certain provisions in the contract and bond documents. Specifically, clauses such as
"Pay-When-Paid" and "Pay-If-Paid" can alter the terms of payment for a given
project, and expose a party to substantial risk of non-payment. To avoid such
unintended consequences, members of the construction industry should carefully
review all documents and ensure that the agreements accurately reflect the
parties' respective intentions. In
addition, a party will be well
served to review the applicable law to be certain that the terms of the
agreements are effective and enforceable and that any procedural requirement is
satisfied.
Ramsey Kazem
404/582-8065
rkazem@smithcurrie.com
Site Directory:
Practice Areas //
Firm Overview //
Office Locations //
Attorneys //
E-Mail //
Articles //
Reported Labor Decisions //
Clients //
Recruiting //
Newsletters //
Seminars //
Guestbook //
Home
|